Parking Garage Demolition
Started: May 17, 2025
Completed: August, 2025
Task | Start | Finish | Duration |
---|---|---|---|
Garage Closed | May 17, 12 a.m. (Midnight) | ||
Babson Enabling Work & Preparations | May 19 | May 23 | 5 Days |
Site Mobilization & Utility Make Safe | May 19 | May 30 | 10 Days |
Demolition | May 26 | August 1 | 10 Weeks |