Parking Garage Demolition

Started: May 17, 2025
Completed: August, 2025
Task Start Finish Duration
Garage Closed May 17, 12 a.m. (Midnight)
Babson Enabling Work & Preparations May 19 May 23 5 Days
Site Mobilization & Utility Make Safe May 19 May 30 10 Days
Demolition May 26 August 1 10 Weeks