Start: May 17, 2025
Projected Completion: August 1, 2025

Summer 2025 parking guidance will be forthcoming.

Task Start Finish Duration
Garage Closes May 17, 12 a.m. (Midnight)
Babson Enabling Work & Preparations May 19 May 23 5 Days
Site Mobilization & Utility Make Safe May 19 May 30 10 Days
Demolition (Tentative) May 26 August 1 10 Weeks